Overview

This unit involves the skills and knowledge required to install and commission photovoltaic (PV) power conversion equipment (PCE) to grid.
It includes working safely to industry installation standards, installing components in accordance with design, placing and securing system components accurately, making required circuit connections, testing and commissioning the installation and completing the necessary installation documentation.
The skills and knowledge described in this unit require a licence or permit to practice in the workplace where work is carried out on electrical installations, which are designed to operate at voltages greater than 50 volt (V) alternating current (a.c.) or 120 V direct current (d.c.).
Competency development activities in this unit are subject to regulations directly related to licensing. Where a licence or permit to practice is not held, a relevant contract of training, such as an Australian Apprenticeship, is required.
Additional and/or other conditions may apply in some jurisdictions subject to regulations related to electrical work. Practice in the workplace and during training is also subject to work health and safety (WHS)/occupational health and safety (OHS) regulations.Note: Those holding an Unrestricted Electrician’s Licence or equivalent issued in an Australian state or territory meet the prerequisite requirements of UEEEL0012 Install low voltage wiring, appliances, switchgear and associated accessories. All other prerequisite requirements must be met.

Assessment

For Melbourne campuses

Assessment tasks will be designed to reinforce & extend knowledge and skill competence within set & controlled parameters in accordance with each unit's learning outcomes & performance criteria requirements, including the setting of work-based practical application tasks designed to provide evidence of competence outcomes, within periodic and scheduled timelines.

Students will be expected to demonstrate the following required skills:

  • applying relevant work health and safety (WHS)/occupational health and safety (OHS) requirements, including using risk control measures
  • verifying design, drawings and documentation and resolving any issues with designer
  • installing grid-connected system safely
  • testing and commissioning in accordance with industry standards and regulations
  • completing documentation according to regulatory and industry standards.

Students will also be expected to demonstrate the following knowledge:

  • power conversion equipment (PCE), including:
  • types of PCEs used in grid-connected systems
  • the basic AC specifications and functions of an PCE
  • PCE operation, including:
  • connection of a grid connected PCE and measurement of the PCE parameters for various loads
  • Industry Standards and regulation relevant to PCEs
  • PV grid-connected system operation, including:
  • operation of grid interactive PV systems, including synchronisation, safety feature, power flow control, passive and active anti-islanding, secondary - protection and metered energy for systems
  • schematic diagrams of common grid-connected PCE circuit configurations, including metering arrangements, isolation and connection with respect to residual current devices (RCDs) in accordance with relevant industry standards
  • installation of grid-connected PCEs, including:
  • major installation requirements for all system components which will ensure correct operation, long life, safety and ease of maintenance consistent with relevant industry standards and WHS/OHS guidelines
  • typical installation configurations for grid connection of energy systems via PCEs
  • the function and operation of a grid protection device as specified by relevant industry standards
  • labelling and signage requirements for switchboards supplied with power from grid connected PCEs, as set out in the relevant industry standards
  • system commissioning and maintenance, including:
  • the isolation procedures required for grid-connected PCEs
  • relevant commissioning procedures, including start-up and shutdown procedures for grid-connected PCE systems in accordance with relevant industry standards
  • testing a grid-connected PCE system for correct operation
  • performing commissioning work on a PV power system in accordance with relevant industry standards.
  • relevant workplace documentation, policies, procedures and standards.

Required reading

The qualified trainer and assessor will provide teaching and learning materials as required in the form of workbooks produced by Victoria University and/or via the Victoria University e-learning system.

As part of a course

This unit is studied as part of the following course(s):

Search for units, majors & minors